Lifehacks

Who signs a construction change directive?

Who signs a construction change directive?

They’re a simple written agreement that incorporates itself into the main contract that states the adjustments in scope, price, and time. These are signed by all parties and become part of the main construction agreement.

What is a construction change directive AIA?

AIA Document G714™–2017 is a directive for changes in the Work for use where the owner and contractor have not agreed on proposed changes in the contract sum or contract time. Upon receipt of a completed G714, the contractor must promptly proceed with the change in the work described therein.

How do change orders work in construction?

Most change orders modify the work required by contract documents (which, in turn, usually increases the contract price) or adjust the amount of time the contractor has to complete the work, or both. For there to be a valid change order, the owner and contractor must both agree on all terms.

When would you use a construction change directive?

Construction Change Directive: The Basics This mechanism is used when the owner and contractor cannot agree on the schedule or budget of the additional work, or when they agree to determine pricing and timing later.

What is the difference between change order and change directive?

For Change Orders, the Owner, through its Consultant, advises the Contractor in writing that a change is required. The Contractor then presents its proposal to address the change in terms of time and cost. Upon receipt of the Change Directive, the “Contractor shall proceed promptly with the change” in the work.

Why might an owner decide to issue a construction change directive?

Who can issue the change directives for a contract?

the Owner
Change Directives (described in GC 6.3) are issued by the Owner when the parties cannot agree to the amount of adjustment required, but the Owner requires the work to proceed nonetheless.

Share this post